§ 28-39.1. Demolition of building and site clearance.  


Latest version.
  • In the event the owner elects to demolish the building pursuant to § 28-39A above, he shall, within 60 days of the occurrence, secure a demolition permit. The building shall be demolished and the site shall be cleared of all debris within 30 days of the issuance of said permit. Site clearance shall include the removal of all debris from the foundation and backfilling with clean inorganic fill.